To increase the efficiency of existing equipment and systems and eliminate bottlenecks, Isfahan Oil Refining Company has put the optimization project of furnaces H1-251~254 and H2-251~254 on the agenda as an EPC.

This project includes two economizers, four fans, and four pumps that should reduce the temperature of the exhaust gas flow of the aforementioned furnaces from about 900°C to below 200°C. The incoming water flow from the boilers is branched and directed to these economizers to increase the efficiency of the boilers.

Hirgan Energy Engineering Company was successful in receiving the above project in the tender for the Isfahan Refining Company in March 1401. After completing the initial process of the project, the KOM meeting was held on 01/27/1402 in the office of the esteemed employer, with the presence of Mr. Kashanian (Project Engineering Manager), Mr. Behzadi (Project Manager), Dr. Bahrami (Chairman of the Energy Committee), Mr. Seifi
(Product Management), Mr. Shariat Madar (Process Supervisor) on behalf of the employer and Mr. Khajovi (Engineering Manager),

Engineer Asghar Nejad (Project Manager), Engineer Amiri (Commercial Manager), Engineer Barloui (Civil, Structural, and Architecture Supervisor), Engineer Zamani (Electrical Supervisor), and Ms. Engineer Aref (Planning Supervisor) were held.